Rubber processing had resulted in elevated metal and hydrocarbon concentrations in soils presenting a potential risk to an adjacent water course. Made ground was excavated, with hand picking to remove deleterious materials, asbestos and waste rubber. Stockpiles were then tested against remedial criteria. Solidification / stabilisation was applied to 6,500m3 of failing materials to reduce contaminant leachability. Over 50 tonnes of soils with >0.1% asbestos were disposed off site, and over 660